Our Experience

Location Details of m/c Description of work Completion time
TATA STEEL LTD KHONDBOND MINES JODA

Unloading and shifting of 8.9 MW DG set at Tata Steel mines Khondbond ,Joda (orrisa)

 Unloading ,shifting at required loacation and alignment of  2 nos 8.9 MW DG STIC at Tata Steel Mines Khondbond ,Joda (Orrisa)

STERLING & WILSON

 Shifting of 10 Mva transformer at IPDS Project Katwa Distt : Bardhaman (WB)

 Unloading and croosing it in truck vehicle shifting it to 33/11 KV substation and dragging it to 300 mtr distance 

10 days
BHILAI ENGINEERING CORPORATION

 Erection of Hyperbloid structure at BARC Mumbai

  Erection of Hyperbloid structureTower of 41 mtr height and erection of Hyperbloid  at BARC Mumbai

Running
GET & D INDIA LTD

132/33 KV AIS S/S Berla (CG) 

 Electromechanical erection of 132/33 KV S/S including Erection of 40MVA Transformer with oil filtration

3 Months
SAMSUNG PROJECT DAICEC (RELIANCE)

 Shifting and Erection of 3 MW x 7 DG Sets

  Shifting and Erection of 3 MW x 7 DG Sets AT DIACEC Project BKC Mumbai

1 Month
GET & D INDIA LTD

 132/33 KV AIS S/S Bhakhara (CG)

 Electromechanical erection of 132/33 KV S/S including Erection of 40MVA Transformer with oil filtration 

6 Months
GE T & D INDIA LTD

Site office construction at 400 KV S/S

 Construction of site office for 400 KV S/S  Kurud ,Distt .Dhamtari (CG)

45 days
DB POWER LTD

 Shifting and placement of GT 250MVA

  Shifting and placement of spare GT  250MVA at BLA Power Ltd 

10 days
GET & D INDIA LTD

Shifting ,unloading of 50 MVA transformer

 Shifting ,unloading, and placing on plinth  of 50 MVA transformer at MRSS site , NMDC JAGDALPUR

15 DAYS
THERMAX INSTRUMENTATION LTD

Transportation ,unloading ,erection and installation of 80 MT Generator at 13 mtr height ,erection of siemens make condenser at 4.5 Mtr height

 Transportation ,unloading ,erection and installation of 80 MT Generator at 13 mtr height ,erection of siemens make condenser at 4.5 Mtr height 2 units each

3 months
BLA Power Pvt Ltd.Gadarwara (MP)

45 MW X 1 TDPS Siemens Make,Steam Turbine Generator

Unloading Installation & Erection on 11 meter height / Siemens make 80 MT Condenser placing upto Height 4.5 meter

22 Days
Tata Steel Kalingana Nagar Odisa

8MW X 5 no. Hyundai Make Engine,315 MVA CGL make Transformer

Installation & Erection

4 month
Reliance (Hajira)

BHEL make 120 MT Condenser and 240 MT Generator

Unloading Installation & Erection on 4.5 meter height

45 days
Steel Authority of India Ltd.(SAIL) Durgapur

110 MT straightening machine Siemens make

Erection of 5 meter height

20 days
Mitsubishi Pvt. Ltd.(Haldiya)

Crompton Greeves make Transformer 125 MVA

Unloading & Erection on plinth

2 days
Rajiv Gandhi International Air port Hyderabad working with GMR office OCTAMECH Engineering Ltd

Flight maintenance bay structure unloading shifting assembly and erection

26mtr height Colum and trusses erection total quantity of structure having weight 2011MT including three flight maintenance bay

From 19Jan to 16/8/2011 Hand over building
O.N.G.C Manglore Refinery and Petrochemical Ltd Manglor Karnatka State Working with M/s Thermax Ltd Pune

1100MT material handling lob (unloading shifting staging verification, issue record maintain )total center store activity 1 x72 MW Project

Total boiler and Turbine related spear unloading and supply to concern contractor (Gas Turbine)

From 09April2011 to next 15th month
M/s DuPont India Ltd.Turkapalli A.p

PEB Pre Engineered Buildg 740Sq.Mtr area

Painting erection shitting,finishing and handover The pre engineered building at Turkapalli Project

3 Months
Orient Paper Mill Amlai Dist Shahdol M.P working with Themax India Ltd Pune

Siemens make Generator Siemens Make condenser Siemens Make Turbine

1x 25MW and 1 x 30 MW Unloding shifting and lifting up to turbine floor

4 Months
Minakshi Energy Pvt .Ltd.Gudur A.P Working with M/s Thermax India Ltd Pune

150MW x 2 Generator stator China make

Stator having 152ton weight shifting up to 80Mtr and lifting up to 11mtr height

From 11June2011 to next 26days target
Ind Bharat Power Ltd Tuticorin T.N Working with Greenesol Power Bangulur

150MW x 2 Generator stator China make

Stator having 152ton weight shifting up to 80Mtr and lifting up to 11mtr height

Till continue
UltraTech cement Ltd. ACW Awarpur cement work dist chandrapur Working with M/s Thermax Ltd.Pune

5000MT material handling job (unloading shifting staging verification, issue record maintain )total center store activity

Total boiler and Turbine related spear unloading and supply to concern contractor

From April 2010 Total Period of contract 17month
UltraTech cement Ltd. ACW Awarpur cement work dist chandrapur Working with M/s Thermax Ltd.Pune

Siemens make 25mw generator having weight 70MT Turbine 20MT Transformer 55MT

Unloading shifting and placing up to proper place Generator and turbine lift and shift up to 11mtr height (CFBC boiler)

30days
Siemens make 40mw generator having weight 92MT Turbine 35MT

Unloading shifting and placing up to proper place Generator

22days
ACC Cement Guggus Dist Chandrapur M.S Working with M/s Thermax Ltd Pune

HEL make 25Mw Generator and De aerator tank Transformer and BHEL make condenser

Unloading shifting and placing up to proper place Generator and turbine lift and shift up to 11mtr height (CFBC boiler)

20Day
UltraTech cement Ltd. ACW Awarpur cement work dist chandrapur Working with M/s Thermax Ltd.Pune

Bhart Bijali make Transformer 70MT

Unloading shifting and placing up to proper place

5days
UltraTech Cement Hirmi Raipur (C.G.)

6MW Wartsila Make engine with ABB Alternator(120Ton)Air base mounting with one base for alternator

6MW Wartsila Make engine with ABB Alternator(120Ton)Air base mounting with one base for alternator

25Days
Gujarat Fero Chemical Ltd Dehej

6MW Caterpillar make engine (65+25 Tons )

6MW Caterpillar make engine (65+25 Tons )

08Days
Madras cement ltd Govindpuram Ariyalur Tamilnadu working with M/s Thermax Ltd Pune

Siemens make 40mw generator having weight 92MT Turbine 35MT condenser 85MT

Unloading shifting and placing up to proper place Generator and turbine lift and shift up to 11mtr

26days
Madras cement ltd R R Nagar Madurai Tamilnadu working with M/s Thermax Ltd Pune

TDPS make 25mw generator having weight 72MT Siemens make Turbine 35MT

Unloading shifting and placing up to proper place Generator and turbine lift and shift up

15days
Vicat Sager Cement (Bharti Cement) Chatrasala Village, Distt Gulbarga

TDPS make 35mw generator having weight 72MT Siemens make Turbine 35MT

Unloading shifting and placing up to proper place Generator and turbine lift and shift up

15days

Clients

ABB INDIA LTD
Chhattisgarh State Power Transmission Company Limited
STERLING & WILSON
GET & D INDIA LIMITED
Rajiv Gandhi Airport
IBPIL
Madras Cements
ONGC
Tata Steel
Sail
Reliance
Siemens
Ultratech
ACC Cements

Shree Ganesh Infrastructure

Office:-C-39 Lokmanya Tilak CHS
Rohinipuram, Raipur (C.G)

Branch:-Office: B 303, Tantra Sangam CHS, Plot No.32, Sector-42, Seawood,
Nerul, Navi Mumbai - 400706,