Location | Details of m/c | Description of work | Completion time |
---|---|---|---|
TATA STEEL LTD KHONDBOND MINES JODA | Unloading and shifting of 8.9 MW DG set at Tata Steel mines Khondbond ,Joda (orrisa) |
Unloading ,shifting at required loacation and alignment of 2 nos 8.9 MW DG STIC at Tata Steel Mines Khondbond ,Joda (Orrisa) |
|
STERLING & WILSON | Shifting of 10 Mva transformer at IPDS Project Katwa Distt : Bardhaman (WB) |
Unloading and croosing it in truck vehicle shifting it to 33/11 KV substation and dragging it to 300 mtr distance |
10 days |
BHILAI ENGINEERING CORPORATION | Erection of Hyperbloid structure at BARC Mumbai |
Erection of Hyperbloid structureTower of 41 mtr height and erection of Hyperbloid at BARC Mumbai |
Running |
GET & D INDIA LTD | 132/33 KV AIS S/S Berla (CG) |
Electromechanical erection of 132/33 KV S/S including Erection of 40MVA Transformer with oil filtration |
3 Months |
SAMSUNG PROJECT DAICEC (RELIANCE) | Shifting and Erection of 3 MW x 7 DG Sets |
Shifting and Erection of 3 MW x 7 DG Sets AT DIACEC Project BKC Mumbai |
1 Month |
GET & D INDIA LTD | 132/33 KV AIS S/S Bhakhara (CG) |
Electromechanical erection of 132/33 KV S/S including Erection of 40MVA Transformer with oil filtration |
6 Months |
GE T & D INDIA LTD | Site office construction at 400 KV S/S |
Construction of site office for 400 KV S/S Kurud ,Distt .Dhamtari (CG) |
45 days |
DB POWER LTD | Shifting and placement of GT 250MVA |
Shifting and placement of spare GT 250MVA at BLA Power Ltd |
10 days |
GET & D INDIA LTD | Shifting ,unloading of 50 MVA transformer |
Shifting ,unloading, and placing on plinth of 50 MVA transformer at MRSS site , NMDC JAGDALPUR |
15 DAYS |
THERMAX INSTRUMENTATION LTD | Transportation ,unloading ,erection and installation of 80 MT Generator at 13 mtr height ,erection of siemens make condenser at 4.5 Mtr height |
Transportation ,unloading ,erection and installation of 80 MT Generator at 13 mtr height ,erection of siemens make condenser at 4.5 Mtr height 2 units each |
3 months |
BLA Power Pvt Ltd.Gadarwara (MP) | 45 MW X 1 TDPS Siemens Make,Steam Turbine Generator |
Unloading Installation & Erection on 11 meter height / Siemens make 80 MT Condenser placing upto Height 4.5 meter |
22 Days |
Tata Steel Kalingana Nagar Odisa | 8MW X 5 no. Hyundai Make Engine,315 MVA CGL make Transformer |
Installation & Erection |
4 month |
Reliance (Hajira) | BHEL make 120 MT Condenser and 240 MT Generator |
Unloading Installation & Erection on 4.5 meter height |
45 days |
Steel Authority of India Ltd.(SAIL) Durgapur | 110 MT straightening machine Siemens make |
Erection of 5 meter height |
20 days |
Mitsubishi Pvt. Ltd.(Haldiya) | Crompton Greeves make Transformer 125 MVA |
Unloading & Erection on plinth |
2 days |
Rajiv Gandhi International Air port Hyderabad working with GMR office OCTAMECH Engineering Ltd | Flight maintenance bay structure unloading shifting assembly and erection |
26mtr height Colum and trusses erection total quantity of structure having weight 2011MT including three flight maintenance bay |
From 19Jan to 16/8/2011 Hand over building |
O.N.G.C Manglore Refinery and Petrochemical Ltd Manglor Karnatka State Working with M/s Thermax Ltd Pune | 1100MT material handling lob (unloading shifting staging verification, issue record maintain )total center store activity 1 x72 MW Project |
Total boiler and Turbine related spear unloading and supply to concern contractor (Gas Turbine) |
From 09April2011 to next 15th month |
M/s DuPont India Ltd.Turkapalli A.p | PEB Pre Engineered Buildg 740Sq.Mtr area |
Painting erection shitting,finishing and handover The pre engineered building at Turkapalli Project |
3 Months |
Orient Paper Mill Amlai Dist Shahdol M.P working with Themax India Ltd Pune | Siemens make Generator Siemens Make condenser Siemens Make Turbine |
1x 25MW and 1 x 30 MW Unloding shifting and lifting up to turbine floor |
4 Months |
Minakshi Energy Pvt .Ltd.Gudur A.P Working with M/s Thermax India Ltd Pune | 150MW x 2 Generator stator China make |
Stator having 152ton weight shifting up to 80Mtr and lifting up to 11mtr height |
From 11June2011 to next 26days target |
Ind Bharat Power Ltd Tuticorin T.N Working with Greenesol Power Bangulur | 150MW x 2 Generator stator China make |
Stator having 152ton weight shifting up to 80Mtr and lifting up to 11mtr height |
Till continue |
UltraTech cement Ltd. ACW Awarpur cement work dist chandrapur Working with M/s Thermax Ltd.Pune | 5000MT material handling job (unloading shifting staging verification, issue record maintain )total center store activity |
Total boiler and Turbine related spear unloading and supply to concern contractor |
From April 2010 Total Period of contract 17month |
UltraTech cement Ltd. ACW Awarpur cement work dist chandrapur Working with M/s Thermax Ltd.Pune | Siemens make 25mw generator having weight 70MT Turbine 20MT Transformer 55MT |
Unloading shifting and placing up to proper place Generator and turbine lift and shift up to 11mtr height (CFBC boiler) |
30days |
Siemens make 40mw generator having weight 92MT Turbine 35MT | Unloading shifting and placing up to proper place Generator |
22days | |
ACC Cement Guggus Dist Chandrapur M.S Working with M/s Thermax Ltd Pune | HEL make 25Mw Generator and De aerator tank Transformer and BHEL make condenser |
Unloading shifting and placing up to proper place Generator and turbine lift and shift up to 11mtr height (CFBC boiler) |
20Day |
UltraTech cement Ltd. ACW Awarpur cement work dist chandrapur Working with M/s Thermax Ltd.Pune | Bhart Bijali make Transformer 70MT |
Unloading shifting and placing up to proper place |
5days |
UltraTech Cement Hirmi Raipur (C.G.) | 6MW Wartsila Make engine with ABB Alternator(120Ton)Air base mounting with one base for alternator |
6MW Wartsila Make engine with ABB Alternator(120Ton)Air base mounting with one base for alternator |
25Days |
Gujarat Fero Chemical Ltd Dehej | 6MW Caterpillar make engine (65+25 Tons ) |
6MW Caterpillar make engine (65+25 Tons ) |
08Days |
Madras cement ltd Govindpuram Ariyalur Tamilnadu working with M/s Thermax Ltd Pune | Siemens make 40mw generator having weight 92MT Turbine 35MT condenser 85MT |
Unloading shifting and placing up to proper place Generator and turbine lift and shift up to 11mtr |
26days |
Madras cement ltd R R Nagar Madurai Tamilnadu working with M/s Thermax Ltd Pune | TDPS make 25mw generator having weight 72MT Siemens make Turbine 35MT |
Unloading shifting and placing up to proper place Generator and turbine lift and shift up |
15days |
Vicat Sager Cement (Bharti Cement) Chatrasala Village, Distt Gulbarga | TDPS make 35mw generator having weight 72MT Siemens make Turbine 35MT |
Unloading shifting and placing up to proper place Generator and turbine lift and shift up |
15days |
Office:-C-39 Lokmanya Tilak CHS
Rohinipuram, Raipur (C.G)
Branch:-Office: B 303, Tantra Sangam CHS, Plot No.32, Sector-42, Seawood,
Nerul, Navi Mumbai - 400706,